At a glance
Mercury broke ground on the NZ$506 million Puke Kapo Hau wind farm west of Dunedin on 10 November 2026, RNZ reported.
The 192MW, 40-turbine project is Stage 2 of the Mahinerangi Wind Farm, which Mercury calls "New Zealand's largest wind farm once complete".
RNZ reported that Mercury had confirmed the decision to approve the expansion was supported by its 140MW power option with Datagrid.
The turbines are due to start generating in the April to June 2028 quarter, the year Datagrid targets for its Makarewa AI campus in Southland.
Datagrid's option covers about 1.2TWh a year, more than twice the 533GWh Mercury expects the new turbines to produce.
Mercury broke ground on the Puke Kapo Hau wind farm in Otago on Tuesday 10 November 2026, RNZ reported, with works due to begin in November. Chief executive Stew Hamilton opened the groundbreaking ceremony with Te Rūnanga o Ōtākou at the 1,700-hectare site, about 50 kilometres west of Dunedin. The NZ$506 million project adds 40 turbines and 192MW to the existing Mahinerangi Wind Farm, according to the company's 16 October release.
The company has linked the timing to a data centre customer. RNZ reported that "Mercury previously confirmed the decision to approve the expansion was supported by the agreement with Datagrid." That agreement is a 15-year option over 140MW for Datagrid's AI data centre campus at Makarewa, north of Invercargill.
Datagrid's option covers about 1.2TWh of electricity a year, more than twice the 533GWh a year Mercury expects Puke Kapo Hau to generate. In its August results, the company wrote that the wind farm "is positioned to support South Island demand, including from Datagrid".
Hamilton made the same link in comments reported by RNZ on 10 November. "Data centres can play an important role in New Zealand's economic growth, but new demand needs to be matched by investment in new electricity generation," he told the broadcaster.
Puke Kapo Hau adds 192MW to a 36MW wind farm
The existing Mahinerangi Wind Farm has run 12 turbines and 36MW since 2011, according to Mercury's project page. Stages 1 and 2 together will have 52 turbines and 228MW, with expected generation of about 646GWh a year, the 16 October release says. RNZ puts it at about 648GWh. That is enough to power the equivalent of 92,000 homes, by the company's estimate.
German manufacturer Nordex will supply 40 of its N133 turbines, each rated at 4.8MW, its 22 October release says. It is Nordex's first order from New Zealand, and the company will service the turbines for 30 years. Higgins and Electronet are Mercury's other key partners on the build.
Te Rūnanga o Ōtākou, the local Māori council, recommended the project's name. Puke Kapo Hau "means simply, the hill that catches the wind," its Ūpoko, or chair, Edward Ellison said, RNZ reported. He described the site in the eastern foothills of the Lammermoor Range as culturally significant for mana whenua, the people with customary authority over the land. The company will also set up an annual community fund for groups around the wind farm.
Up to 200 people will work on the site each day at peak construction. Once running, the wind farm will employ around eight to 10 full-time staff, Hamilton said, according to RNZ.
Mercury broke ground four months after welcoming fast-track approval
Puke Kapo Hau was approved under the Fast-track Approvals Act, the law that sends nationally significant projects to an expert panel for a single decision. Mercury welcomed the approval on 3 July 2026. It was the sixth renewable energy project approved under the process, according to a joint release from ministers Chris Bishop and Simeon Brown.
The company's board approved the investment in August 2026. It then issued a notice to proceed, the instruction that releases contractors to start work, on 16 October, after it completed grid connection studies with Transpower. The groundbreaking came 25 days later.
The August results presentation puts the cost at NZ$2.6 million per megawatt, against NZ$3.1 million and NZ$3.7 million per megawatt on its two most recent wind farms. The build is funded from the company's own balance sheet.
Puke Kapo Hau will be the first wind farm built under the fast-track law, according to Mercury. The same process is now handling the 100 Halsey Street data centre plan at Wynyard Quarter in Auckland.
Datagrid's 140MW option runs for 15 years
The 140MW agreement was announced by Datagrid on 18 March 2026. The two companies call it a power purchase option agreement. Datagrid describes it as a long-term price hedge, and Mercury says it gives Datagrid flexibility ahead of its final investment decision.
"The PPOA reflects that the data centre is currently in the development phase and gives flexibility in advance of a final investment decision," according to Mercury's 2026 integrated report. Datagrid expects to commit to the Makarewa build before the end of 2026, as we reported on 9 November.
Earlier, in July, Mercury had bought a 12.7 per cent stake in Datagrid for NZ$53 million, and Hamilton joined its board. We covered that stake on 23 July.
Hamilton told analysts on 18 August that Mercury is "lining that up pretty closely with our ability to deliver Puke Kapo Hau", referring to Datagrid's 2028 target, as we reported at the time. The current schedule has generation starting in the April to June 2028 quarter and running in full by the end of 2028. Nordex plans to commission the first turbine in mid-2028.
Horizontal works at Makarewa began on 18 August, and Datagrid targets full delivery of its 280MW first stage in 2028. Datagrid has also pre-paid Transpower for transformers at a new Makarewa substation.
Project | Owner | Size | Timing |
|---|---|---|---|
Puke Kapo Hau wind farm, Otago | Mercury | 192MW, 40 turbines, about 533GWh a year | Groundbreaking 10 November 2026, works begin November; full generation expected by the end of 2028 |
Mahinerangi Stages 1 and 2 combined | Mercury | 228MW, 52 turbines, about 646GWh a year | Stage 1 operating since 2011 |
Power option for Makarewa | Datagrid and Mercury | 140MW, about 1.2TWh a year, 15 years | Agreed March 2026; an option ahead of Datagrid's investment decision |
Makarewa AI campus, Southland | Datagrid | 280MW first stage | Horizontal works since 18 August 2026; delivery targeted for 2028 |
Source: Mercury release of 16 October 2026, results presentation of 18 August 2026 and 2026 integrated report; Datagrid release of 18 March 2026 and website; RNZ, 10 November 2026. Figures are as each source states them and are not all measured on the same basis.
Mercury's chief links new supply to lower power prices
Hamilton tied new supply to lower wholesale prices. "Over the past year we've seen wholesale electricity prices fall significantly, with average spot prices dropping from around $196 per megawatt hour to $79 per megawatt hour," he said, according to RNZ. "By developing demand and supply together, New Zealand can support growth while maintaining energy security and helping manage long-term electricity costs," Hamilton said.
We expect more data centre power deals in New Zealand to come paired with new generation, as Datagrid's has, because National, Labour, the Greens and the Opportunity Party all want large AI data centres to secure their own supply. We set out those party policies on 9 November.
What to watch
Datagrid's investment decision: Datagrid expects to commit to the Makarewa build before the end of 2026. Under Mercury's integrated report, the option gives Datagrid flexibility until that decision.
First turbines, early 2028: Nordex is scheduled to begin installing turbines in early 2028, with Mercury's first generation expected in the April to June 2028 quarter.
Official election result, 27 November: the Electoral Commission releases the official count, and coalition talks then decide which party's data centre power rule the next government takes up.