At a glance
Goodman NZ holds Auckland Council consent for a two-storey data centre at its Penrose Industrial Estate, BusinessDesk reported on 12 November 2026.
BusinessDesk put the data centre's IT load at 24MW, a large building by New Zealand standards.
A works agreement for a 32MVA power connection is signed, with power on site expected in the first half of 2028.
About NZ$20 million is committed to design and power works, in what the company calls a "staged approach".
Half-year results on 23 November are the next chance for an update on the site.
Goodman NZ, the NZX-listed industrial property company, has a consented data centre site in the Auckland suburb of Penrose, BusinessDesk reported on 12 November 2026. Auckland Council granted the resource consent on 11 February 2026, the outlet reported.
At 24MW of IT load, the Penrose design is larger than the roughly 15MW central Auckland data centre NEXTDC withdrew from consenting in October. BusinessDesk said that "with an IT load of 24 megawatts it is still a large data centre by NZ standards."
All work on the site is "intended to preserve optionality", BusinessDesk wrote. Development general manager Mike Gimblett told the outlet the company was taking a measured approach to Penrose. Chief executive James Spence put it this way at the May results. "Our investment at Penrose reflects a disciplined, staged approach that is consistent with our broader capital allocation," he said.
A 32MVA connection is due on site in the first half of 2028
Spence gave the power position at the annual meeting in July. "With an approved data centre resource consent and a works agreement for a 32MVA power connection now signed, we anticipate an on-site power connection in the first half of 2028," he said in his address to shareholders.
MVA, or megavolt-amperes, is the unit used to rate a grid connection. The connection is larger than the IT load because cooling and other building plant draw power too.
Penrose is one of four Auckland data centre connections in delivery on Transpower's October list. We reported the list on 3 November. It shows a 30MW Goodman connection at Penrose through Vector, the Auckland lines company. The list gives a due date of 30 September 2028.
In May 2025 the company set out a NZ$20.2 million investment in a 35MVA connection, with power expected by mid 2027. Its May 2026 results gave the target as 32MVA in the first half of 2028, with a works agreement "expected shortly". It was signed by the July meeting.
Consented plans allow a 6,856sq m data hall at Penrose
The consent documents describe a two-storey data centre with a gross floor area of 9,592sq m, including a 6,856sq m data hall, BusinessDesk reported.

The plant list runs to 18 transformers, 24 chillers and 18 backup generators, with storage for up to 324,000 litres of diesel.
The 8.8-hectare estate is a working industrial site, 100 per cent occupied at 31 March according to the company's May results. Winstone Wallboards and Independent Traffic Control are named as its key customers there. BusinessDesk reported that existing buildings on the data centre site would be demolished.
Goodman NZ can draw on Goodman Group's data centre expertise
The company runs an industrial portfolio valued at NZ$4.9 billion, including assets it manages, according to its May results. Its 2025 annual report says it "completed a first-generation facility for IBM at Highbrook in 2011".
In February 2024 the company, then Goodman Property Trust, told RNZ it was studying about 50 hectares of brownfield industrial land in South Auckland for data centres. The 2025 annual report then named Penrose as a suitable location.
Goodman Group, the ASX-listed property group and Goodman NZ's largest shareholder, runs a data centre programme of its own. Its September quarter update put its global power bank at 6.6GW, with 3.6GW secured. On 9 November it and Digital Realty confirmed a 9.9 per cent stake in NEXTDC, the ASX-listed operator, as we reported from their ASX notice.
The NZ company can draw on that expertise through its services agreement with the group, the annual report says. It adds that "a development ready site with the necessary infrastructure and consents reduces delivery risk and provides potential operators with speed to market advantages."
Four Auckland data centre connections are in delivery through Vector
Transpower's October list, as we reported, has all four running through Vector. Alongside Penrose they are TenPeaks and Spark at Takanini, CDC at Silverdale and Microsoft at Henderson.
RP Financial has lodged a fast-track application for a Wynyard Quarter development that includes a data centre, and NEXTDC withdrew its central Auckland consent bid in October.
"New Zealand's renewable electricity profile and growing requirement for digital infrastructure support the long-term potential of the sector," Gimblett said.
At 24MW the design sits below hyperscale
On our read, a building of this size suits a colocation operator or one large cloud or enterprise tenant, rather than a hyperscale campus. It would add to an operating colocation market of around 208MW across the country, on research firm Arizton's June 2026 study, as we reported in August.
We expect the company to line up an operator or anchor tenant before it commits to construction, because it calls its approach staged and its spend so far covers design and power only.
Both National and Labour campaigned on data centres bringing their own power, and a site with a signed connection has its grid link in train. Any own-power rule would come on top of that.
What to watch
Half-year results, 23 November: any update on Penrose, a customer or a build decision.
Transpower's next connection list: whether the Penrose date of 30 September 2028 moves closer to the company's first-half 2028 target.
First half of 2028: the on-site power date given to shareholders in July.