AI leadership is a second job at 26% of New Zealand firms
Datacom's 2026 index finds 91% of New Zealand organisations using AI and 4% using it to change core operations. 22% have a dedicated AI leader.
1 September 2026
Datagrid says Makarewa will need fewer than 34 of 84 generators
Datagrid says its Southland data centre will need fewer than 34 of the 84 diesel generators its approvals allow, and under 66 million litres of water a year, mostly rainwater.
22 August 2026
Transpower is assessing a gigawatt of data centre connections
Transpower has taken 30 approaches from data centre developers about connecting to the national grid, and the eleven now being assessed add up to a gigawatt.
22 August 2026
Mercury says data centre demand will outrun what it can build
Mercury has optioned one Southland data centre 1.2 terawatt hours a year, more than the three power stations it finishes by December 2026 will add between them.
21 August 2026
Datagrid begins construction at its 280MW Makarewa campus
HEB Construction has started the roading and earthworks at Datagrid's Makarewa campus north of Invercargill. The platform for the data centre, the cable landing station and the substation is due by the end of 2026.
18 August 2026
New Zealand's AI infrastructure enters its gigawatt decade
New Zealand's colocation fleet runs to about 208MW on Arizton's count, with 530MW on the table. The New Zealand Gigawatt Decade sets out what a gigawatt build returns.
18 August 2026
BCG puts NZ$70 billion on New Zealand's data centre decade
A room of 250 in Auckland agreed what New Zealand should build by 2030. On published benchmarks, a single gigawatt of it costs about NZ$64 billion and 6TWh a year.
14 August 2026
Egypt's Elsewedy Electric wins Datagrid's transformer order
Datagrid's Southland transformers come from Egypt's Elsewedy Electric. US lead times run to four years, and the next New Zealand project needing a grid connection buys from the same market.
14 August 2026
Datagrid pre-pays Transpower for four Southland transformers
Transpower says Datagrid has paid in full and up front for the four transformers behind a 360MVA Southland substation, targeted for commissioning in late 2027.
13 August 2026
New Zealand's data centre protests target unbuilt projects
Stop Data Centres NZ picketed an Auckland summit on 12 August and wants hyperscale approvals paused. New Zealand's first 280MW campus is targeted for 2028.
13 August 2026
Contact is prepared to own half the Stratford data centre
Contact and CDC will seek consent for a 250MW data centre at Stratford, put at NZ$4.5b to NZ$5b by UBS. Infratil holds 49.72% of CDC and 9.08% of Contact.
12 August 2026
Data Centre Leaders Summit NZ 2026 meets on power and consent
New Zealand's data centre industry meets at Cordis Auckland on 12 August, with Chorus, Transpower, Datacom, DCI, Vertiv, Brookfield and Invest New Zealand on the programme.
10 August 2026
New Zealand's 208MW data centre market, operator by operator
New Zealand runs about 208MW of colocation across 36 facilities. Who operates it, what each one sells, and the five public records that show what any site discloses.
5 August 2026
Chorus to sell precise time over its fibre network from 2027
Chorus will sell precision timing over its fibre network from early 2027, aimed at mobile cores, trading systems and databases racked inside New Zealand data centres.
5 August 2026
Morrison in exclusive talks on Orange's French data centres
Orange frames its French data centre venture as strengthening Europe's digital sovereignty. The equity would come from Wellington, where Morrison manages more than US$30 billion.
4 August 2026
Galasso says New Zealand's distance is now its advantage
In an exclusive Q&A, Rémi Galasso says New Zealand's remoteness is now its advantage, and that Datagrid will put firm Makarewa water numbers on the table within weeks.
4 August 2026
Datagrid signs the South Island's first international cable
Datagrid has signed ASN and OMS Group to build the Tasman Ring Network's first phase, 2,300km from Invercargill to Melbourne, with service targeted for 2029.
31 July 2026
Luxon rejects AI data centre pause, orders new rules
The Greens want a one-year pause on consenting new AI data centres. The Prime Minister ruled it out the same day, then put Nicola Willis and his department to work on a rulebook.
29 July 2026
Mercury takes 12.7% equity in Datagrid's Southland AI campus
Mercury has paid US$30m for 12.7% of Datagrid, its first outside shareholder since BW Digital left, making the Southland campus's power supplier a part-owner.
23 July 2026
New Zealand lands its largest AI cloud contract: US$1.32bn from Sharon AI
Sydney neocloud Sharon AI will serve a global AI lab from New Zealand under a US$1.32bn deal, the largest AI compute contract disclosed for the country. The site, the power and the customer are not yet named.
20 July 2026
New Zealand's data centres: who is building, and what is at stake
New Zealand's government wants up to NZ$35bn for AI data centres. The country has 154MW built and one consented project: Datagrid's 280MW Southland campus.
20 July 2026