At a glance

  • Meridian Energy has invested US$30 million for an 11.27 per cent stake in Datagrid, the company building a 300MW data centre at North Makarewa in Southland.

  • The two companies have signed a 140MW power purchase option. If called, it would run for 15 years from a start between 1 July 2028 and 1 January 2029.

  • The option needs clearance from the Electricity Authority before it can take effect.

  • Chief executive Mike Roan joins Datagrid's board, four months after Mercury took a 12.7 per cent stake for the same US$30 million.

  • The data centre holds resource consent, and Datagrid has still to make its final investment decision.

Meridian Energy has bought 11.27 per cent of Datagrid Holding Group NZ for US$30 million, the generator told the NZX and ASX on 26 November 2026. Datagrid is developing a 300MW data centre at North Makarewa in Southland, and Meridian chief executive Mike Roan has joined its board.

"Meridian has worked with Datagrid since 2020, and by directly investing we are supporting employment and economic development in a region where we have a deep and longstanding relationship," Roan says in the announcement. The project is a large source of long-term electricity demand, and he described it as support for the company's "ongoing investment in new renewable generation".

Together, the 140MW power options signed by Meridian and Mercury total 280MW, against the 300MW the two companies now give for the data centre.

Meridian signs a 15-year power option for the Southland campus

Alongside the share deal, the two companies signed a 140MW power purchase option. That is an agreed supply deal that starts only if it is taken up. If called, it would run for 15 years and start between 1 July 2028 and 1 January 2029.

That option is conditional on clearance from the Electricity Authority under its rules for materially large contracts. Those rules stop a generator from offering a very large power user a subsidised deal that leaves other consumers paying more, according to the authority's guidelines. The guidelines set the line at 150MW, and they allow related contracts with the same buyer to be counted together.

Clearance is voluntary under the rules, and Meridian's option is signed on the condition that it gets it. The company is "supporting growth alongside the needs of existing consumers, energy affordability and security of supply", Roan says.

Mercury paid the same US$30 million for 12.7 per cent in July

Mercury made its own investment in Datagrid on 23 July, paying US$30 million, or NZ$53 million, for 12.7 per cent of the same company. In March it had signed a 140MW power option with Datagrid, and that deal helped it approve its Otago wind farm. In NZ dollars, Meridian's price came to NZ$54.6 million, 1News reported.

Together, the two generators have now put US$60 million of equity into Datagrid. When Mercury invested in July, interest.co.nz described the Southland data centre as a NZ$3.5 billion build. That spending waits on Datagrid's final investment decision.

The announcement says the two generators invested at different stages of the project and on different terms. Those terms differ in particular on the share of Datagrid each may end up holding, so the two percentages do not compare directly.

In July, Mercury chief executive Stew Hamilton joined Datagrid's board, so both generators now have their chief executive on it. According to Datagrid, Meridian generates from hydro and wind, and Mercury from hydro, geothermal and wind. With both on board, Datagrid is now partnered with "two of NZ's leading renewable generators", chief executive Rémi Galasso said.

Site works at North Makarewa began in August

When the project launched in 2020, its first partner was Meridian, according to Galasso. Since then, Datagrid has won resource consent for the site. It began construction in August with the horizontal works that prepare the ground, after Galasso said in July that the Mercury partnership would let Datagrid "begin horizontal construction works on the site".

The campus has carried different figures as the design developed. Meridian and Datagrid now give 300MW. Mercury's July release gave 360MW, and Datagrid's website still lists 280MW across three modules. Galasso told us in July that the 360MW is grid capacity, not the data centre's size. In August he added that "our engineers are still optimising the design".

The campus is designed for a PUE of 1.1

In its own words, the campus is "AI infrastructure at scale and cooled by Southland's natural climate", with a design target of a PUE of 1.1. PUE, or power usage effectiveness, compares the total power a data centre draws with the power its computers use. A figure of 1.1 means cooling and other overheads add about 10 per cent on top of the computers' own use.

Galasso tied that design to what AI customers now look for. "As AI drives global demand for compute and electricity, where that power comes from and how efficiently it is used are becoming deciding factors for customers, investors and communities," he said.

Meridian is courting more big power users like Datagrid

The generator calls the deal an important step in its strategy to help grow New Zealand's economy. It has put together a team to look at other large new users, including smelters, mineral processing and green fertiliser.

Its development pipeline holds about 8.8 terawatt hours of secured development options and 6.5 terawatt hours of advanced prospects, which it puts at more than a third of New Zealand's current electricity demand. Roan sees room for more projects like this one. "Datagrid could be the first of many new and varied businesses that we can attract to our shores to create jobs and grow regional economies in a low-emissions manner," he said.

What to watch

The Electricity Authority's clearance. The 140MW option takes effect only once the authority clears it under the materially large contracts rules.

Datagrid's investment decision. Mercury's July release expected Datagrid's final investment decision later this year.

The option window. If the option is called, supply starts between 1 July 2028 and 1 January 2029.