At a glance
RP Financial's full fast-track application plans a standalone data centre with 15MW of IT capacity at 100 Halsey Street in Auckland's Wynyard Quarter, BusinessDesk reported.
The referral-stage plan had a data centre of 35MW at first, rising to 88MW, with a new electrical substation.
The smaller design needs no new substation, and the documents set aside NZ$10 million for new 22kV feeders to supply it.
The fast-track documents estimate the domestic development cost at NZ$910 million, including NZ$205 million for parts of the data centre build.
The application plans construction on two buildings from 2028, with both finished by the end of 2029.
Singapore fund manager RP Financial has scaled back the data centre it plans for its Wynyard Quarter office precinct to 15MW, down from the 35MW rising to 88MW it proposed when the project entered fast-track. The new figure comes from the full application the company lodged under the fast-track consenting process in late October, BusinessDesk reported on 26 November 2026.
The plan is for a standalone data centre alongside four office buildings of nine to 12 storeys at 100 Halsey Street. The figures are IT load, the power the servers and network equipment draw, before cooling. "The project has changed between the referral and substantive application stages," BusinessDesk said.
At 15MW, the Wynyard Quarter data centre is now on a similar scale to the 15MW data centre NEXTDC planned between Nelson and Hobson Streets in central Auckland. NEXTDC withdrew its consent bid for that site in October.
Vector backs a smaller plan that needs no new substation
The earlier plan gave one of the five buildings the option of holding the data centre with an indoor electricity substation. The 15MW design needs no new substation. The fast-track documents put NZ$10 million towards new 22kV feeders to supply the data centre, according to BusinessDesk. A feeder is a power line that carries electricity from a substation to a site. At Westgate, by contrast, Vector is building a new substation for Microsoft's second data centre.
Vector is the lines company for central Auckland, and it wrote a letter of support to the fast-track panel. "The project presents an opportunity to support continued growth and investment in Wynyard Quarter," the company said. It added that "the proposed electricity infrastructure will also provide opportunities to reinforce the surrounding network and support future development in the area."
RP Financial's country head, Luke Kinney, wrote to the Environmental Protection Authority about how the site fits the market. He put New Zealand's live data centre capacity at about 172MW, with 90 per cent of it in Auckland but "almost none in the city centre, where power-enabled sites are scarce". Research firm Arizton measures the market a different way. Its June 2026 study counts about 208MW of colocation, and we used it to map the market operator by operator.
Parts of the data centre build make up NZ$205 million of a NZ$910 million estimate
According to the fast-track documents, the precinct has an estimated domestic development cost of NZ$910 million, BusinessDesk reported. That includes NZ$205 million for parts of the data centre build and the NZ$10 million for the feeders.
The future tenant would supply a further NZ$308 million of servers and other active IT equipment. The economics assessment leaves that equipment out of the cost-benefit case behind the application. Other non-domestic costs were left out too, taking the total development cost to more than NZ$1 billion.
Those figures use a different base from the referral-stage assessment, which put the version with the data centre at NZ$1.164 billion, so the two totals do not compare directly.
Construction on the precinct could start in 2028
The precinct would be built in stages, in part so NZ Bus can keep storing buses on the site under its lease. Construction on the first two buildings could start in 2028 and be finished by the end of 2029, the application says. A third building is due in 2030, subject to leasing.
Work on the last two buildings is planned from 2035, once the NZ Bus lease expires, with estimated completion in 2036 and mid-2037.
"Building 2 will provide low-latency compute capacity alongside the country's largest concentration of financial, professional and technology firms," Kinney wrote. He said the closed-loop cooled data centre was a particularly important part of the development. The company is investigating recovering waste heat from the data centre as an energy source for the neighbouring buildings, BusinessDesk reported.
RP Financial calls 100 Halsey Street its flagship New Zealand project
"The 100 Halsey Street masterplan is our flagship New Zealand development," Kinney wrote. RP Financial describes itself as "a multifaceted group headquartered in Singapore". It bought the 1.7-hectare leasehold site for NZ$55 million, its first purchase in New Zealand, RNZ reported in December 2025.
For the office buildings, the target is a 5 Star Green Star rating. Green Star is the building rating scheme run by the New Zealand Green Building Council. RP Financial said it has engaged with Auckland Council and mana whenua, and its team includes architects Peddlethorp and development manager Neoscape. Ministers referred the project into the fast-track process in July. Under the Fast-track Approvals Act, an expert panel rather than the council decides the application.
What to watch
The expert panel. An expert panel has yet to be appointed to decide the application, BusinessDesk reported.
A tenant for the data centre. The economics assessment says a future tenant would supply NZ$308 million of servers and other IT equipment for the data centre, BusinessDesk reported.
The 2028 start. The application's programme plans construction on the first two buildings from 2028.