At a glance
Infratil's half-year results list a 250MW data centre that CDC and Contact Energy are exploring at Stratford in Taranaki, and repeat that 350MW of transmission capacity could be available there within one to two years.
Contact has said it is prepared to own up to half of the project, and that consent, a tenant and finance could land within a year.
In Auckland, a new 30MW grid connection for CDC at Silverdale is at Transpower's delivery stage, with power estimated for 19 April 2027.
CDC's half-year earnings reached A$339 million, and Infratil raised its full-year forecast to NZ$1,370 million to NZ$1,440 million.
A NZ$256 million provision for incentive fees, tied to CDC's higher value, left Infratil with a NZ$248 million half-year net loss.
Infratil has held up a proposed Stratford data centre as an example of how its portfolio companies can work together. Its half-year results on 18 November describe "CDC and Contact Energy exploring a 250MW data centre development in Stratford, New Zealand".
The results presentation repeats the figure Contact gave in August, that "Stratford has 350MW transmission capacity available within 1-2 years with minimal substation work".
Stratford would be CDC's first New Zealand campus outside Auckland.
Contact could own up to half of the Stratford data centre
Infratil has held a stake in Contact Energy since July 2025, now about 9 per cent, and owns close to half of CDC. Contact said in August that it was prepared to own up to half of the Stratford data centre, and in September that consent, a tenant and finance could land within a year.
Stratford is listed as "proposed" in the results.
A new 30MW Silverdale connection is due in April 2027
In Auckland, CDC runs three data centres across its Silverdale and Hobsonville campuses. Transpower's 8 November list of connection projects shows a new 30MW connection for CDC at Silverdale, through lines company Vector, at the delivery stage. It is in detailed design, with power estimated for 19 April 2027.
Silverdale is one of four Auckland data centre connections at Transpower's delivery stage, alongside TenPeaks and Spark at Takanini, Microsoft at Henderson and Goodman at Penrose.
CDC added 90MW and lifted its own forecast
Across Australia and New Zealand, CDC's half-year earnings rose 84 per cent to A$339 million, and it raised its full-year forecast to A$730 million to A$770 million, from A$710 million to A$750 million. "During the half, CDC delivered another 90MW of operating capacity and Longroad delivered almost 600MW," chief executive Jason Boyes said.
Contracted capacity reached 1.1 gigawatts, with 625MW of new contracts signed during the half. Infratil expects the 1.1 gigawatts to deliver annualised EBITDAF of A$2.2 billion once fully deployed, by the end of the 2029 financial year. The first building at CDC's Laverton campus in Melbourne began operating in October.
Demand growth has remained "exceptionally strong" since the September investor day, according to Infratil's interim report, "but there is some moderation of earlier forecasts for new computing capacity, data centres and energy". The report puts that down to businesses taking longer to embed AI, more selective customers and lenders, and rising regulatory requirements for new data centres. In Infratil's view, that favours developers with grid connections and a record of delivery.
Group operating earnings guidance went up to NZ$1,370 million to NZ$1,440 million for the year to March 2027, from NZ$1,320 million to NZ$1,420 million at the investor day in September.
A fee tied to CDC's value led to a net loss
The bottom line was a net parent loss of NZ$248 million for the half, against the NZ$606 million surplus Infratil reported a year earlier. The loss came from a NZ$256 million accounting provision for incentive fees, which Infratil said was driven by "a large increase in CDC's equity valuation". The final amount of any fees depends on valuations at the end of the financial year.
What to watch
Stratford. A consent application, a tenant or a final investment decision would move the project on from "proposed".
Silverdale. Transpower's next connection list will show whether the 30MW connection holds its April 2027 date.
Year-end valuations. The incentive fees behind the half-year loss depend on them, and CDC's is the largest part.